Waste to Electricity solution delivered to Lahti, Finland
In 2010 BMH successfully modified the existing biomass and SRF handling system ready for the then upcoming gasification plant project. The new SRF handling system for the gasification plant was a turnkey project including receiving and screening of SRF, metal separation and fully automatic sampling systems, reduction of oversize fractions by means of TYRANNOSAURUS® T1202L Shredders, automatic fuel storage and dosing & feeding to gasifiers.
Kymijärvi Power Plant is now the largest SRF using plant in Finland (250,000 t/a).

Customer: | Lahti Energia Oy, Finland |
Category: | Power plant, Gasification |
SRF receiving capacity: | 2 x 600 m3/h, 250 000 tpa |
SRF preparation capacity | 2 x 600 m3/h |
SRF storages volume: | 2 x 7 500 m3 |
SRF boiler feeding capacity: | 40-400 m3/h / 80 t/h |
Main equipment: | SRF receiving and screening with automatic sampling, TYRANNOSAURUS® BioScreen and metal separation, TYRANNOSAURUS® T1202L Shredders, storage silos with TYRANNOSAURUS® Screw Reclaimers, aluminium separation, conveyors to the gasification plant day silos. |
Start-Up: | 2012 |
Gasifier size: | Total fuel power 169 MWth, District heat power 90 MW and electricity power 50 MW |